REM PROCESS1

밤의화신 2013.09.11 14:49 조회 수 : 5399

Regarding SPRO settings, creating REM Profile in T Code OSP2---> here you have to make the seetings

 
related to Costing whether you want to use Standard Cost estimate or using the preliminary costing data

 
from the product cost collector for backflushing,whether you want to execute the correction in dialog mode

 
mandatory or optional,whether you want to create Post processing records individually(you can see the

 
error good's movement's list in COGI) or cumulated one (you will be finding only in MF45,46 or MF47) and

 
the planned order reduction and the Good's movements.

 
Goods issue          261     Goods issue/reversal      262

 
Goods receipt        131     Goods receipt/reversal    132

 
Scrap                551     Scrap/reversal            552

 
By-product           531     By-product/reversal       532

 
The sequence in REM is

 
1.MM01-material creation.(MM01- FERT,HALB,ROH Types),in MRP4 view you have to include the REM

 
allowed indicator and the REM profile assigned for all the Inhouse manufactured items.

 
2.CS01 - BOM creation.(CS01- Create BOM's for your FERT & HALB).

 
3.Work centre creation.(CR01)

 
4.Rate routing.(CA21 - For In house manufactured HALB & FERT's).

 
5.Creating production version to link BOM & Rate routing.(Using MM02 - MRP4view or else C223).

 
6.Creations of product cost collector using production version.(KKF6N,KKF6M).

 
7.Cost rollup & Release using CK40N.

 
8.Demand values (MD61 - Planned Independent Requirements),

 
9.MRP Run(MD02 - Single Item Multi Level),

 
10.Planned orders generated(Checked in MD04).

 
11.Pull List MF60(Using Planned orders to stage the material).

 
12.You can get the reservation number's in MB25,made for 311 movement,using MF65,you can transfer the

 
materials agianst the reservation number.

 
13.MFBF(Assembly Backflush - 261 & 131,Component Backflush - 261,Activity Backflush for extra time

 
spent for the operations).

 
14.Settlement - KK87-month end if any variance.

 
In addition to the above Planning table(MF50) can be used for adjusting the values as per to the capacity

 
availability.

번호 제목 글쓴이 날짜 조회 수
447 <img src=b.gif>계속 남아있는 Debugger창 없에기(New Debugger)[추천:e-abap][추천:보나][추천:버미!] [14] 해처리 2011.01.07 8165
446 Number Range Object 변경/삭제 [4] file MadMax 2010.12.07 8164
445 BAPI_PO_CHANGE [1] 노름마치 2009.09.03 8139
444 Dynamic Internal Table [5] sapjoy 2007.02.11 8092
443 요약파일1 [7] file 밤의화신 2013.09.11 8039
442 Internal Table 알아보기 [15] file 양키 2010.12.20 8000
441 색상 정리 파일. [15] file 공백 2012.03.08 7973
440 CBO 테이블 데이터 UPLOAD 프로그램 [5] sapjoy 2006.12.21 7952
439 메세지 팝업창 뛰워주는 Function [2] file 양키 2013.08.19 7897
438 유지보수 view 생성 후 Field selection 화면 나오게 하려면? [7] file 나침반친구 2007.08.08 7896
437 평가영역 에서 자재 평가는 불일치성 합니다(이전전기시 에러) [1] sapjoy 2007.07.03 7867
436 [Function]달력 팝업창을 뛰워보자 [14] file 양키 2010.10.07 7830
435 [덤프해결] CX_SY_READ_SRC_LINE_TOO_LONG file 양키 2013.08.16 7791
434 온라인 스크린에서 SELECT-OPTION 사용하기 [1] sapjoy 2007.02.11 7786
433 move 구문 [4] sapjoy 2006.12.02 7730
432 What Are Lock Objects ? D.Y.Kim 2007.07.20 7687
431 ALV에 아이콘 넣는 방법 [1] 푸른밤 2007.07.31 7614
430 BAPI_RESERVATION_CREATE1 MB21의 예약생성시 사용하세요. [2] 노름마치 2007.12.10 7604
429 SALV Webdynpro for abap tutorial [6] Wise 멘토 2011.11.15 7601
428 SAP Netweaver 설치 시스템사양 Tip [1] 양키 2012.09.21 7541