REM PROCESS1

밤의화신 2013.09.11 14:49 조회 수 : 5399

Regarding SPRO settings, creating REM Profile in T Code OSP2---> here you have to make the seetings

 
related to Costing whether you want to use Standard Cost estimate or using the preliminary costing data

 
from the product cost collector for backflushing,whether you want to execute the correction in dialog mode

 
mandatory or optional,whether you want to create Post processing records individually(you can see the

 
error good's movement's list in COGI) or cumulated one (you will be finding only in MF45,46 or MF47) and

 
the planned order reduction and the Good's movements.

 
Goods issue          261     Goods issue/reversal      262

 
Goods receipt        131     Goods receipt/reversal    132

 
Scrap                551     Scrap/reversal            552

 
By-product           531     By-product/reversal       532

 
The sequence in REM is

 
1.MM01-material creation.(MM01- FERT,HALB,ROH Types),in MRP4 view you have to include the REM

 
allowed indicator and the REM profile assigned for all the Inhouse manufactured items.

 
2.CS01 - BOM creation.(CS01- Create BOM's for your FERT & HALB).

 
3.Work centre creation.(CR01)

 
4.Rate routing.(CA21 - For In house manufactured HALB & FERT's).

 
5.Creating production version to link BOM & Rate routing.(Using MM02 - MRP4view or else C223).

 
6.Creations of product cost collector using production version.(KKF6N,KKF6M).

 
7.Cost rollup & Release using CK40N.

 
8.Demand values (MD61 - Planned Independent Requirements),

 
9.MRP Run(MD02 - Single Item Multi Level),

 
10.Planned orders generated(Checked in MD04).

 
11.Pull List MF60(Using Planned orders to stage the material).

 
12.You can get the reservation number's in MB25,made for 311 movement,using MF65,you can transfer the

 
materials agianst the reservation number.

 
13.MFBF(Assembly Backflush - 261 & 131,Component Backflush - 261,Activity Backflush for extra time

 
spent for the operations).

 
14.Settlement - KK87-month end if any variance.

 
In addition to the above Planning table(MF50) can be used for adjusting the values as per to the capacity

 
availability.

번호 제목 글쓴이 날짜 조회 수
307 SAP Tuning-실무 [11] file 대전희망 2008.06.20 3537
306 workflow - purchase order의 예 [2] file gauguin 2008.06.25 3675
305 <b>[완료]</b>sap netweaver 라이센스 문제... [4] 아밥초짜 2008.06.25 4545
304 튜닝자료.. [16] file 세인 2008.07.11 4767
303 클라이언트간 CTS로 데이타이관 [15] file 노름마치 2008.07.11 11094
302 레포트에서_파일_대화상자_띄우기 [3] file xcomedy 2008.07.19 4478
301 Number_Range_사용법 [13] file xcomedy 2008.07.19 3539
300 <b>[완료]</b>netweaver 설치중 오류log 원인 아시는분 좀 알려주세요 [1] 카즈키 2008.07.19 5264
299 테이블컨트롤에서 F4 값 변경시 다른 필드 값도 변경하기 F4IF_INT_TABLE_VALUE_REQUEST [1] 한해동안 2008.07.24 9421
298 <b>[완료]</b>New abap editor block selection 기능 아시는분... [11] file 숨어푸 2008.08.01 5039
297 Open SQL 문법 정리 [14] SAP질 중 2008.08.20 10850
296 abap email report source [7] file SAP질 중 2008.08.22 4706
295 [re] TABLE, DEIVERY CLASS 정보 테이블 궁그미 2008.09.02 4182
294 ABAP Program Tips v3 [13] file 2008.09.04 5827
293 여러 DATE 변환 TIP [9] file 푸른창공 2008.09.11 5061
292 ALV 버퍼 CLEAR 프로그램 [10] sapjoy 2008.09.25 7381
291 Abap에서 ftp command 를 실행시킬수 있는지 [1] 쿠도스 2008.10.09 4435
290 Screen painter가 열리지 않는 경우, tip [2] darkangel 2008.10.21 5565
289 ABAP FAQs [3] 해처리 2008.10.24 3991
288 Abap Eclipse Editor [5] file franticlion 2008.11.03 6168